(Repost) The future of project controls




By Pat Weaver on Mosaicproject’s Blog (2016)


Last week I participated in two PUXX panel discussions in Perth and Sydney focused on predicting the influence of technology on project controls.  The range of subjects covered ranged from drones and remote monitoring to virtual reality.

Many of the topics discussed offered better ways to do things we already do, provided we can make effective use of the data generated in ever increasing quantities – significant improvements but essentially ‘business-as-usual’ done better. The aspect I want to focus on in this post is the potential to completely reframe the way project schedules are developed and controlled when existing ‘gaming technology’ and BIM are synthesised.

The current paradigm used for critical path scheduling is a (dumbed-down) solution to a complex set of problems required to allow the software to run on primitive mainframe computers in the late 1950s – the fundamentals have not changed since! See: A Brief History of Scheduling.

The underlying assumption is a project consists of a set of activities each with a defined duration and depending on the logical relationship between the activities, some are ‘critical’ others have ‘float’.  The basic flaw in this approach can be demonstrated by looking at the various options open to a schedule to define the work involved in 3 simple foundations involving excavation and mass concrete fill.


All four of the above options above are viable alternatives that may be chosen by different schedulers to describe the work using CPM, and none of them really describe what actually happens. The addition of more links would help but even then the real situation which is one resource crew visits three locations in turn and excavates the foundations, a second crew follows and places the concrete with some options for overlapping, parallel working and possibly synchronising the actual pouring of all three foundations on the same day…….. Optimising the work of the crews is the key to a cost effective outcome and this depends on what follows their work.  For more on resource optimisation see: www.mosaicprojects.com.au/Resources_Papers_152.html. Advances in computer software offer the opportunity to develop a new way of working.

The starting point for the hypothesis outlined I this post is 4D BIM (Building Information Modelling). Last month I was in London working on the final edits to the second edition of the CIOB’s book, Guide to Good Practice in the Management of Time in Complex Projects (due for publication in 2017 as The Management of Time in Major Projects). One of the enhancements in the second edition is an increased focus on BIM. To assist our work a demonstration of cutting edge 4D BIM was provided Freeform.

Their current capabilities include:

  • The ability to model in real time clashes in working space provided the space needed for each crews work is parameterised. Change the timing of one work crew and the effect on others in a space is highlighted.
  • The ability to view the work from any position at any time in the construction process; allowing things such as a tower crane driver’s actual line of sight to be literally ‘seen’ at different stages of the construction.
  • The relatively normal ability to import schedule timings from a range of standard tools to animate the building of the model, and the ability to feedback information derived from processes such as the identification of clashes in the use of working space using
  • The space occupied by temporary works and various pieces of equipment can be defined and clashes with permanent works identified over time.
  • Finally the ability for a person to see and move around within the virtual model using the same type of 3D virtual reality goggles used by many gaming programmes. The wearer is literally immersed in the model.

Moving into the world of game playing, there are many different games that allow players in competition, or collaboration, to ‘build’ cities, empires, fortifications, farms, etc. These games know the resources available to the players and how many resources will be required to construct each new element in the game – if you don’t have the resources, you can’t build the new asset.

Combining these two concepts opens up the possibility for a completely new approach to scheduling physical projects that involve the deployment of resources to physical locations to undertake work. The concept of location-based scheduling is not new, it was used in the 1930s to construct the Empire State Building (see: Line of Balance) and is still widely used.  For more on location-based scheduling see: Location-Based Management for Construction: Planning, Scheduling, and Control by Prof. Russell Kenley.

How these concepts tie into BIM starts with the model itself.  A BIM model consists of a series of parameterised objects. Each object can contain data on its size, weight, durability, cost, maintainability, carbon footprint, etc. As BIM develops many of these objects will come from standard libraries created by suppliers and subcontractors. Change an object, for example, replace windows from manufacturer “A” with similar Windows from manufacturer “B” and the model is update and potential issues with sizes, fixings and waterproofing can be identified. It is only a small step from this point to add parameters related to the resources needed to undertake the work of installation.

With this information and relatively minor enhancements to current BIM capabilities, once the engineering model is reasonably complete a whole new paradigm for planning work opens up.




Continue reading on mosaicprojects.wordpress.com